Roof on, cladding up, services roughed in, and the last look inside the walls.
Lock-up is where damage done by following trades is still attributable. On Box Hill jobs we have recorded studs cut and damaged after the frame was signed off, cables run hard against hot water pipes without the clearance they need, and parapet capping and sarking details that will be behind cladding within days. It is also where we confirm what was actually rectified from the frame list.

Annotated findings from Lock-up (pre-plaster) inspections on Box Hill builds. Client addresses withheld.




1Bored piersAfter boring and cage placement, before any concrete
2Slab pre-pourThe day before the pour, steel and formwork complete
3FrameOnce frame and trusses are up and the roof is on, before lining
5FixingAfter mouldings, doors and joinery, before the painter
6WaterproofingAfter the membrane is applied and before any tile is laid
7Pre-handover (PCI)Two to three weeks before your handover dateInstant online pricing, or talk to the booking team on 1300 471 805.
Because it passed before the damage happened. A stud cut by a plumber or electrician after frame stage is carrying less than it was designed to, and the frame inspection that signed it off cannot have seen it.
A clearance is required for good reason. Sustained heat against cable insulation degrades it, and it is a two minute fix while the wall is open and effectively unfixable afterwards.
Yes. The stage is defined by services being complete and linings not yet up, which here lasts only a handful of days.
Every one of them. The report carries a reassessment marking each earlier item fixed, partly fixed or outstanding.
Around two hours plus the report, longer on a double storey or a complex roofline where more of the capping and flashing has to be reached.
We inspect what is still open and state plainly which areas could not be seen. An honest partial inspection beats a full one you only think you got.